From Our Correspondent
Amaravati: Amaravati’s capital city construction has reached 31.9% physical progress against a planned milestone of 53.8%, indicating a significant execution gap despite an acceleration in works over the past month.
According to the latest APCRDA contractor review as of 28 June 2026, two contractors—KMV Projects and MVR Infra—are ahead of schedule, while the remaining six continue to lag behind their respective targets.
Construction in Amaravtati has reached 31.9% physical progress against a planned milestone of 53.8%
This is according to the latest contractor-wise execution review by the Andhra Pradesh Capital Region Development Authority (APCRDA) as of 28 June 2026.
The overall progress improved by 1.5 percentage points compared to the previous review held on 29 May 2026.
The review shows that while most contractors continue to trail their scheduled targets, KMV Projects and MVR Infra have exceeded their planned milestones.
Among the major contractors:
KMV Projects recorded the highest progress at 37.8%, surpassing its target of 35.2%.
MVR Infra achieved 35.9% against a target of 34.5%.
BSR Infratech reached 31.6% compared to its target of 41.5%.
Shapoorji Pallonji reported 30.3% against 40.9%.
NCC Ltd achieved 28.4% versus a target of 44.2%.
RVR Projects stood at 25.8% against 38.7%.
Larsen & Toubro (L&T) recorded 24.8% compared to a target of 50.9%.
MEIL registered 20.5% against 34.8%.
The review also noted month-on-month progress across all contractors, with improvements ranging between 1.1 and 1.6 percentage points since the previous assessment on 29 May.

Investments exceed ₹45,000 crore
As per the review, the total investment committed to the ongoing works has risen to ₹45,362 crore, an increase of ₹2,634 crore over the previous review. The number of active project packages has also increased to 96, with six new packages added during the review period.
The newly awarded packages include:
Secretariat Landscaping & External Works – Package IV
High Court Building – Internal Finishes Package II
Amaravati RR Roads – Phase II (Additional Stretch)
Kondaveeti Vagu – Left Side Protection Works – Package II
Capital City Underground Drainage – Package II
Utility Duct & Service Corridors
Despite the gap between actual progress and planned targets, APCRDA data indicates that construction activity has accelerated over the past month, with additional packages being awarded and investments continuing to rise. During the latest review of Amaravati works by Chief Minister Chandrababu Naidu, Minister P. Narayana confirmed that 26,924 workers and over 5,140 heavy machines are actively engaged in various project sites across the capital.


1 Comment